OLDCASTLE GLASS

Wright City, MO

Nova Group, Inc. was responsible for Architectural, Civil and Structural foundation design for this new 65,000 S.F. Manufacturing Facility including master planning, 5,300 S.F. office layout and structural foundations.  The building frame and enclosure consisted of a pre-engineered steel building system supplied by others.

The site issues coordinated with the design team’s civil engineer included truck access, drainage, phased building additions and future parking.

The Phase 2 addition completed in January 2007 and totaling 22,000 S.F., provides new truck docks, an additional manufacturing line, support space and a new employee parking lot.  An 11,000 S.F. Phase 3 Addition was completed in the fall of 2007 and the 5,000 S.F. Phase 4 Addition was recently completed in November of 2008. The facility now totals 103,000 S.F.

Completion Date: November 2008
Construction Cost:  $4,000,000